Software engineeringbasic
Which scheduling tool is described as a horizontal bar chart?
Answer
Gantt chart
Explanation
### Why this is right
A Gantt chart is described as a horizontal bar chart used as a production control tool and frequently used in project management.
### The concept
A bar-chart representation can show project activities across time. It differs from a WBS, which decomposes work hierarchically, and from CPM, which analyzes activity relationships and project duration.
### The other options
- **B. Work Breakdown Structure (WBS)**: This is a hierarchical breakdown of project work, not the horizontal bar chart described.
- **C. Critical Path Method (CPM)**: This is an activity-oriented scheduling technique.
- **D. Risk item checklist**: This supports risk identification, not schedule display.
### Terms
- **Gantt chart**: A horizontal bar chart used in project scheduling and control.
- **Production control**: Organizing and tracking the work needed to produce an output.
### Remember
Bars across a schedule indicate a Gantt chart.
Related Questions
- Software is described as engineered rather than manufactured in the classical sense.(basic)
- Explain why software engineering is broader than programming.(intermediate)
- Known risks are risks that can be uncovered through careful evaluation of the project plan.(basic)
- A team has stable, well-defined requirements and chooses a sequential process with clearly separated phases. Which model best matches this situation?(intermediate)
- Select ALL qualities identified as attributes of good software.(basic)
Want to practice more questions like this?
Join myBenkio free and practice past questions for your Nigerian university courses with AI explanations for every answer.
Start Practicing Free