Critical Path Method (CPM) is described as activity-oriented and deterministic.

Answer

true

Explanation

### Why this is right Critical Path Method (CPM) is identified as an activity-oriented technique and a deterministic model. It supports schedule preparation and resource planning. ### The concept CPM focuses on project activities and uses fixed estimates in the model as described in the material. The critical path determines the total project duration. This differs from PERT, which is described as event-oriented and probabilistic. ### Terms - **Deterministic model**: A model that uses fixed, rather than probabilistic, estimates. - **Critical path**: The sequence of activities that determines the project's total duration. ### Remember CPM is activity-oriented and deterministic; PERT is event-oriented and probabilistic.