Software engineeringintermediate
Critical Path Method (CPM) is described as activity-oriented and deterministic.
Answer
true
Explanation
### Why this is right
Critical Path Method (CPM) is identified as an activity-oriented technique and a deterministic model. It supports schedule preparation and resource planning.
### The concept
CPM focuses on project activities and uses fixed estimates in the model as described in the material. The critical path determines the total project duration. This differs from PERT, which is described as event-oriented and probabilistic.
### Terms
- **Deterministic model**: A model that uses fixed, rather than probabilistic, estimates.
- **Critical path**: The sequence of activities that determines the project's total duration.
### Remember
CPM is activity-oriented and deterministic; PERT is event-oriented and probabilistic.
Related Questions
- Software is described as engineered rather than manufactured in the classical sense.(basic)
- Explain why software engineering is broader than programming.(intermediate)
- Which scheduling tool is described as a horizontal bar chart?(basic)
- Known risks are risks that can be uncovered through careful evaluation of the project plan.(basic)
- Select ALL qualities identified as attributes of good software.(basic)