In software engineering project management, which of the following is a recognized core principle of project scheduling?
Answer
Compartmentalization of the project into discrete tasks
Explanation
### Why this is right
- **Compartmentalization**: Scheduling separates a project into activities.
- **Interdependency**: It recognizes relationships among activities.
- **Defined responsibilities**: Work needs assigned ownership.
- **Defined milestones**: Progress needs identifiable points.
### The concept
The material also names time allocation, effort validation, and defined outcomes. A schedule coordinates work; it does not eliminate communication.
### The other options
- **E. Eliminating all communication**: This is not a scheduling principle and would undermine coordination among people and tasks.
### Terms
- **Milestone**: A defined point used to mark progress or completion of work.
### Remember
A useful schedule connects activities, time, effort, owners, outputs, and milestones.
Related Questions
- Software is described as engineered rather than manufactured in the classical sense.(basic)
- Explain why software engineering is broader than programming.(intermediate)
- Which scheduling tool is described as a horizontal bar chart?(basic)
- Known risks are risks that can be uncovered through careful evaluation of the project plan.(basic)
- Select ALL qualities identified as attributes of good software.(basic)
Want to practice more questions like this?
Join myBenkio free and practice past questions for your Nigerian university courses with AI explanations for every answer.
Start Practicing Free